BALLPARK COSTING FOR GENERAL ITEMS

[NOT TO BE USED FOR PROJECT SPECIFIC DESIGN OR FINAL BID ASSESSMENT - THIS IS A GUIDE ONLY]
  • Superintendent                                                    $ 4,760.00 per week
  • Project Management Team - PM/PE                   $ 2,560.00 per week
  • Demolition                                                            $ 2.25 per square foot
  • Debris Boxes                                                        $ 1,142.00 each
  • Colorcore Casework w/ SS Tops                        $ 950.00 per lineal foot
  • Banquette                                                             $ 1,200.00 per lineal foot
  • Doors and Frames                                               $ 2,250.00 each
  • Glass                                                                     $ 25.00 per square foot
  • Glass Doors                                                          $ 4,165.00 each
  • Drywall                                                                  $ 30.00 per square foot
  • Tiling                                                                      $ 20.00 per square foot
  • Acoustical Ceilings                                               $ 8.00 per square foot
  • Carpet Tile                                                            $ 4.50 per square foot
  • Resilient Flooring                                                 $ 12.00 per square foot
  • Floor Prep                                                             $ 1.25 per square foot
  • Painting                                                                 $ 3.00 per square foot
  • Code Signage Allowance                                   $ 500.00 allowance
  • Mechoshades / Room blinds                              $ 30.00 per square foot
  • Window Film                                                        $ 20.00 per square foot
  • Wet Sprinkler System Reconfiguration              $ 2.50 per square foot
  • HVAC Allowance - Reconfigure existing           $ 15.00 per square foot
  • Electrical                                                               $40.00 per square foot
  • Temp Power & Lighting                                      $ 0.75 per square foot
  • Construction Contingency                                 10.0 %  
  • Overtime Contingency                                       10.0 %
  • Job Site Requirements                                       5.0 %
  • Building Permit Allowance                                 4.0%
  • Liability Insurance                                               1.0 %
  • Fee – Percentage                                               4.5 %